Summary of Como fazer a Análise de Valor Agregado | Robson Camargo
Summary of "Como fazer a Análise de Valor Agregado | Robson Camargo"
Main Ideas:
- Added Value Analysis: This is a crucial project management tool that compares planned progress, actual progress, and expenses to assess project performance.
- Key Variables:
- Planned Value (PV): The budgeted amount for work scheduled to be completed by a specific time.
- Actual Cost (AC): The actual amount spent on the project up to a specific time.
- Earned Value (EV): The value of work actually completed by a specific time.
Methodology and Key Concepts:
- Understanding the Basics:
- Added Value Analysis helps in determining project status in terms of time and budget.
- It is essential for project managers and is widely used in various companies.
- Example Breakdown:
- Initial Scenario: A project budget of R$ 1 million over 10 months, with a planned expenditure of R$ 100,000 per month.
- After 3 Months:
- Planned spending: R$ 300,000
- Actual spending: R$ 100,000
- Without EV, one cannot ascertain project status.
- Determining Project Status:
- If only meetings were held costing R$ 200,000 against a planned cost of R$ 1,000, the project is significantly off track.
- If R$ 100,000 was spent completing all planned activities, the project is ahead.
- Calculating Key Performance Indicators:
- Schedule Variance (SV): SV = EV - PV
- A negative SV indicates the project is behind schedule.
- Schedule Performance Index (SPI): SPI = EV / PV
- An SPI less than 1 indicates the project is behind schedule.
- Cost Variance (CV): CV = EV - AC
- A positive CV indicates the project is under budget.
- Cost Performance Index (CPI): CPI = EV / AC
- A CPI greater than 1 indicates cost savings.
- Schedule Variance (SV): SV = EV - PV
- Re-estimating Project Costs and Duration:
- New estimates can be calculated based on performance indices.
- Two formulas for estimating future costs:
- Based on specific savings observed.
- Based on cost performance index projections.
- Estimating Remaining Work:
- Two estimates for remaining costs and durations can be derived from the current status and performance indices.
- The methodology can also apply to hours instead of monetary values.
Conclusion: The video emphasizes the importance of Added Value Analysis in project management, providing a structured approach to assess and control project performance.
Speakers/Sources Featured:
- Robson Camargo (Main speaker and educator on the topic of Added Value Analysis)
Notable Quotes
— 03:02 — « Dog treats are the greatest invention ever. »
Category
Educational