Summary of "#Aerated #Concrete #Wall Laying, How to design and built (with underfloor heating) #1/20"

Main Ideas and Concepts

Methodology and Instructions

  1. Preparation:
    • Assemble upper slab formwork.
    • Apply electric lines before pouring slab concrete.
  2. Wall Construction:
    • Pour slab concrete.
    • Apply cement-based glue to the under-wall.
    • Start wall construction by applying glue to joints (maximum thickness of 1mm).
    • Complete the first row of blocks and apply glue to the top for the second row.
    • Slide half aerated concrete blocks into place.
    • Use lintels for door and window openings.
  3. Utility Installation:
    • Fill the gap at the ceiling with PU foam.
    • Carve channels for electrical installations.
    • Install casing and junction box assemblies.
    • Run data, telephone, satellite, and electric lines within the wall.
  4. Surface Preparation:
    • Tyrolean the wall with mortar before plastering.
    • Create plaster guides and complete cement-based plastering.
  5. underfloor heating Installation:
  6. Final Finishing:
    • Pour screed for leveling.
    • Apply gypsum finish plaster and paint primer.
    • Apply the first coat of paint.
    • Adhere solid parquet with adhesive.
    • Install door frame and door leaf, securing with polyurethane foam.
    • Fix door jambs and attach door accessories.
    • Mount wooden skirtings and roll on the final coat of paint.
    • Attach electrical fixtures and clean the area for moving in.