Video summary
How To Create a Project Charter
Main summary
Key takeaways
Main ideas / lessons conveyed
-
Purpose of a Project Charter: A project charter is an early, lightweight document (format may vary) that:
- Introduces people to the project—especially new team members after assignment.
- Creates alignment/agreement on key project aspects (e.g., objectives, scope, budget).
- Enables approval to proceed with project planning by circulating the final draft for signatures.
-
Why it’s needed: Even if an organization uses different terms (e.g., project request, Scope of Work/SOW), the charter-equivalent helps reduce misalignment caused by different perspectives.
-
How detailed it should be: Because it’s drafted before real planning, it shouldn’t be detailed. The recommendation:
- Target size: 5 pages or less (ideally “less”).
- Rationale: If people can’t read it quickly, it won’t achieve its purpose.
-
What perspective misalignment looks like: The video uses cartoons/examples (e.g., old lady vs. young woman; “Tree Swing” cartoon) to show that different stakeholders often picture different outcomes—described as “one of the biggest killers of projects.”
-
How to create it effectively: The charter creation process matters as much as the document—best done with a facilitated session involving the sponsor and team members.
-
Where to get a free template: A download is available at the end via PMPerspective.com, with membership required.
Methodology / instructions (checklist)
1) Define what a “project charter” is in your context
- Recognize that a project charter may be called different things depending on the organization:
- Can be a Word document, PowerPoint, etc.
- Charter may be equivalent to:
- Project request (internal)
- Scope of Work (SOW) (external clients)
2) Use the charter for three core purposes
- Introduce people to the project (especially new team members).
- Align stakeholders on the most important elements:
- objectives
- scope
- budget
- (and other critical aspects)
- Obtain approval to proceed with planning:
- send the final draft for signatures
- use that approval to begin project planning
3) Keep the charter short and “planning-light”
- Draft it early (before detailed planning exists).
- Include only enough information to describe:
- the project
- the product/solution it will create
- Recommended length:
- ≤ 5 pages
- Avoid very long charters (example given: “50 pages”) because no one reads them.
4) Include specific sections/information in the charter
Background
- Explain what an outsider/stakeholder needs to understand why the project is a good idea, such as:
- industry trends
- company challenges/turnaround
- strategic direction from leadership/board
Scope
- Describe the end product/solution at a high level.
- Describe key actions the team will take (examples):
- design/build the product
- test it
- market and sell a number of units
- Define boundaries:
- what the project team is responsible for
- where the project begins and ends
- Explicitly state what the team will NOT do if confusion is likely, e.g.:
- the team designs/builds/tests, but sales/revenue targets are not the project team’s responsibility
Objectives
- Ensure objectives are measurable.
- Example:
- Bad: “Significantly increase sales revenues” (ambiguous)
- Good: “Increase sales revenues by 15% by the end of Fiscal Year 2014” (verifiable)
People / Roles
- Include a “who’s who” section:
- PM, sponsor, and project team members (or leads for larger teams)
- Add enough detail so readers know who to contact for questions (e.g., environment for product development, testing approach).
Key dates / milestones
- Provide target/estimated timeline items.
- Clarify these are guesses/targets (since detailed plans/design may not exist yet).
- Still, an initial timeline can influence the approach.
Costs
- Provide cost estimates/targets (to be verified later).
- Break costs by fiscal year, including:
- one-time execution costs
- ongoing costs and maintenance
Constraints, Assumptions, Risks, Dependencies
- Constraint: an external/internal factor limiting or dictating parts of the project (examples):
- an event must occur May–September due to snow in winter
- limited staffing (only one developer; no outside help)
- Assumption: conditions relied upon to achieve objectives (example):
- the ERP system will be used for the next five years (enabling productivity gains)
- Risk: anything that could block delivery (example):
- hurricane risk disrupting/damaging construction
- Dependency: something that must happen for deliverables to meet objectives (example):
- hotel construction completion needed before an opening-night event
5) Follow a recommended drafting process
-
Who should create it
- Don’t draft in isolation.
- Best practice: bring sponsor and team together in a facilitated session.
-
How to run the charter session
- Facilitate a Project Charter session.
- Step through charter sections and ask probing questions.
- Record answers on a flip chart/whiteboard.
- Let differences in perspective surface—alignment through discussion is valuable (team-building aspect).
-
After the session
- Draft the charter back at your desk using the captured information.
-
Feedback and sign-off
- Send out a draft and request feedback from the team.
- Incorporate feedback, then circulate for signatures.
- At minimum, both the PM and the sponsor sign.
6) Use a free template at the end (optional)
- Go to: www.pmperspective.com/resources/templates
- Click initiation phase to expand.
- Find the project charter template and click download template link.
- Note: download may require PMPerspective membership (free sign-up); no sharing/spam stated.
- The video also provides a link to the templates page.
Speakers / sources featured
- PM Perspective video host (speaker): “PM Perspective” channel representative providing guidance on project charters and templates.
- PMPerspective.com (resource site/source): templates and membership for downloading a project charter template.