How to Baseline a Project Scope - Project Management Training
Main summary
Key takeaways
How to Baseline a Project Scope (Business/Process Summary)
Core idea
- Baseline = the difference between success and failure in project management.
- A baseline is created after defining the scope and getting stakeholder approval, then used to monitor and track performance throughout the project.
Step 1: Define the project scope (document it)
Use a scope statement that includes:
- What the project will produce (description of the scope / resulting deliverables)
- Major deliverables produced during and as a result of the project
- Assumptions that may affect scope
- Constraints that may impact scope
Then integrate with:
- Work Breakdown Structure (WBS)
- WBS breaks the scope into work at a high level, then into more detailed work packages.
- Those work packages are used to:
- Build the schedule
- Estimate the cost
- WBS Dictionary
- Provides more detailed descriptions per work package
Step 2: Approve the scope (formal sign-off)
- Who approves? Stakeholders (often one or multiple, depending on project size)
- Common structure/process mentioned:
- Change Control Board (CCB)
- Uses the organization’s change control process to review and ensure the scope meets objectives.
- Handling changes: If anything needs to change, it is handled during the review/approval stage.
- After approval: the approved scope becomes the project baseline.
How the baseline is used (execution/control)
- Once baselined, the baseline is used to monitor and track the project throughout its lifecycle.
- The goal is to maintain alignment to the agreed scope; changes should go through the change control process.
Frameworks / Processes Referenced
- Scope Statement (definition of scope, deliverables, assumptions, constraints)
- Work Breakdown Structure (WBS) (scope decomposition)
- WBS Dictionary (detail for work packages)
- Change Control Board (CCB) / Change Control Process (governance for scope approval and changes)
- Project Baseline (reference point for monitoring/control)
Metrics / KPIs / Targets Mentioned
- No explicit business KPIs or numeric targets were provided in the subtitles.
Concrete Tools / Recommendations
- The presenter suggests using a project management software tool to baseline project scope:
- ProjectManager.com (call to sign up)
Presenters / Sources
- Presenter: “Hello everyone” / unnamed speaker (no name provided in the subtitles)
- Source mentioned: ProjectManager.com (software/tool reference)