Video summary
Building a Silver Mine in Mexico, But Can Costs Stay Under Control? | GoGold Resources CEO Interview
Main summary
Key takeaways
Business / Strategy Overview (GoGold Resources)
- Core thesis: Build a silver–gold district in Mexico anchored by an operating tailings cash engine (Peral, Chihuahua), while executing Las Rico South first, then scaling via Las Rico North.
- Operating + development model:
- Peral tailings retreatment provides free cash flow to fund general support while Los Rico is constructed.
- Las Rico South is moving from permitting into construction (main near-term value driver).
- Las Rico North is a parallel future expansion path (studies + permitting leading to the next construction decision).
Key Playbook / Process Elements (De-risking Build Time)
Execution readiness playbook
- Consolidate/validate historical data: digitize old reports and archives.
- Complete detailed engineering (~85% complete) before/around permitting.
- Order long-lead equipment early: e.g., SAG mill ordered ~6 months prior.
- Secure EPCM and underground development contractor: let key construction contracts early.
Study staging / risk framing
- PA → PEA/Pre-feasibility → Feasibility, with explicit uncertainty ranges:
- PA: ±50%
- Pre-feasibility: ±25%
- Feasibility: ±10%
District build timeline sequencing
- “First pour” milestone in South, while North permitting/engineering advances concurrently so the build team can roll forward.
Concrete Asset Details & Examples
Las Rico South (flagship build)
- Type: Low sulfidation epithermal silver–gold vein system
- Location: ~100 km northwest of Guadalajara, Jalisco, Mexico
- Permitting: Final SEMARNAT approval received ~2 months before interview; construction approved
- Feasibility (Jan 2025):
- ~91M ounces silver equivalent at ~276 g/ton (silver equivalent basis)
Operating economics framing (CEO explanation)
- LOM build target: 24 months to reach first pour
- Ramp to full commercial production: +6 months (about a ~6-month ramp)
- Mining approach: bulk underground (sublevel longhole; remote stope operations; paste backfill to stabilize ground)
- Mill approach: 2,000 tons/day whole ore leach plant producing dore bar, sold at ~99.5% of spot (not a concentrate model)
Las Rico North (next expansion leg)
- Status: Has a PA; intended to follow South into construction once the first mine operates
- Planned contribution (CEO-provided):
- North expected to add ~8.8M silver equivalent ounces/year
- District goal target: 15–17M silver equivalent ounces/year at all-in costs ~US$12/oz (CEO framing)
Peral Tailings Operation (cash engine)
- Location: Chihuahua State (tailings retreatment)
- Life: ~4 years remaining (CEO statement)
- Scale / operations:
- ~12 years continuous production (first pour June 2014)
- Monthly run-rate (approx.):
- ~30,000 oz silver/month
- ~400 oz gold/month
- Cost framing: about US$4M/month (CEO statement)
- Technology / differentiation:
- Elomirated heat leach of tailings + cement/pelletization into heaps
- SART to regenerate sodium cyanide and produce saleable copper/zinc precipitates (Samsung cited as buyer)
- Cash flow claim:
- At current commodity prices, ~US$80–90M/year after costs
- About ~US$60M after tax mentioned later for broader project context
Key Metrics & KPIs / Targets Explicitly Stated
Project execution targets
-
Las Rico South
- First pour: ~24 months after build initiation
- Ramp to full commercial production: +6 months
- Detailed engineering: ~85% complete at time of interview
- Largest portion of build: underground + mill + paste backfill
-
Cost / break-even KPI
- AISC: ~US$12/oz silver equivalent (explicit “all in sustaining is 12 bucks” threshold)
Production growth KPIs (district-level)
- Peral: producing silver equivalent to support district build
- Los Rico South (post-build):
- Adds ~7.2M silver equivalent ounces
- Combined with existing Peral production: ~9M silver equivalent oz/year at top-quartile costs (~US$12) (CEO statement)
- Los Rico North (future):
- Adds ~8.8M oz/year (projected)
- District target: ~15–17M oz/year at ~US$12 all-in cost (CEO statement)
Financing / balance sheet KPIs
- Cash on hand: ~US$284M at end of quarter (CEO statement); no debt stated
- Capex estimates:
- Feasibility capex: ~US$227M (study)
- Inflation uplift (~18 months): ~US$260M expected
- Execution tracking: “around $255 left to spend” after EPCM tracking
- Free cash flow support (Peral):
- ~US$80–90M after costs
- CEO also connects interest on bank balances to covering G&A (exploration and overhead)
Economic Drivers, Sensitivities, and “What Changed”
NPV / feasibility vs earlier study
- CEO states economics weakened from PA/earlier work to feasibility, despite improved grades/resources, attributing this to:
- Reduced study uncertainty (PA vs feasibility maturity)
- Mining method change: earlier plan contemplated an open pit with high strip ratio economics; political/social climate drove a shift to bulk underground with a smaller tail-end open pit
- Discount rate / study framework and social acceptance constraints
Inflation and updated pricing framing
- Feasibility does not fully bake in inflation, but metal price sensitivity exists.
- Inflation assumption: ~8–10% in Mexico
- Study ~18 months old → capex uplift to ~US$260M
“Bare minimum” viability
- CEO indicates the project works down to their AISC threshold:
- Break threshold: ~US$12 silver equivalent
- A “50% drop” scenario was described as still workable under their AISC framework (no additional hard numbers beyond the AISC threshold provided)
Operational Tactics & Technical Execution Details (Actionable Items)
-
Underground critical path: development rates and access/portal timing
- Portal timing: first 4–5 months of the 24-month build
- Ore for commissioning: produce enough earlier than first pour (but not immediately at full 2,000 t/d)
- Ramp strategy: mill not at full rate at first pour; ~6 months added to reach full commercial
-
Underground mine method: bulk longhole/sublevel longhole with paste backfill for:
- Stability
- Reduced pillar loss (optimize extraction vs leaving pillars)
-
Early ore generation allowed by permit:
- Hill slope stabilization / portal area activities to generate early feed
- References to “slab off” hillside stabilization
-
Geotechnical de-risking:
- WSP used for feasibility geotechnical work
- Additional geotechnical drilling (20+ holes) during construction to confirm:
- Portal location stability
- Hanging-wall conditions
-
Mining dilution & recovery:
- Feasibility sensitivity cited: ~30% plan dilution manageable for grades/structure width
- Recovery stated around ~90%; metallurgy “not a challenge”
Sales / Marketing / Investor Relations (High Level)
- CEO says they continue to market/communicate for transparency with shareholders, even while claiming no near-term equity is needed.
- Messaging/catalysts emphasize execution updates and district progress; North permitting and study progression expected to drive valuation later.
Risk Register (Business Execution Emphasis)
- Primary risks
- Commodity price risk (mitigation via margin positioning)
- Underground execution risk (considered higher than mill construction)
- Safety (explicitly top priority)
- Community/social license risk (mitigation: early community engagement; unanimous support per CEO)
- Water risk (mitigation: underground water sources; dry-stacked tails; water balance discussed)
- Geotechnical surprises (mitigation: extra drilling; WSP program; paste backfill; stability management)
- Capital/financing risk (mitigation via cash + no debt + engineered scope; CEO says no equity raise unless capex ~US$400M)
- Security risk (CEO reports no security issues over 30 years in Mexico and describes government responsiveness if threats arise)
Specific Financing / Equity Raise Logic
- CEO asserts:
- No need to return to market for equity under normal capex outcomes
- Capex “blowout” threshold: if capex reached ~US$400M, they’d likely revisit financing
- Revolving credit facilities discussed as “insurance” (with carrying costs), but preferred not to use
Presenters / Sources
- Interviewee / source: Brad Nichol, CEO & President, GoGold Resources
- Host / interviewer: Antonio (host of the Resource Talks interview series)