What is the Critical Path Method (CPM)?
Main summary
Key takeaways
Summary
The Critical Path Method (CPM) is a project-planning and monitoring technique that represents activities and their dependencies in a network. It helps project managers understand a project’s logic, estimate its duration, identify activities that could delay completion, and track progress.
CPM was developed in the 1950s by Morgan Walker of DuPont and James Kelly of Remington Rand. The video says its roots reach back to the 1940s, including its use on the Manhattan Project. CPM and the related Program Evaluation and Review Technique (PERT) use similar underlying approaches but display information differently:
- CPM: Activities are shown as boxes or nodes connected by arrows that indicate dependencies. Traditionally, CPM uses one duration estimate per activity.
- PERT: Activities are shown on arrows, with nodes marking their connections. PERT uses three-point duration estimates.
The video notes that PERT is used less often today.
The Six-Step CPM Process
- Specify the activities. Identify the project activities, usually using the work breakdown structure.
- Sequence the activities. Determine the dependencies that link activities.
- Draw the network diagram. Show activities as boxes and use arrows to represent their logical relationships. Boxes can also contain other relevant information.
- Estimate activity durations. CPM traditionally uses a single duration estimate for each activity. This keeps the method simple but does not explicitly account for uncertainty or variability.
- Identify the critical path. The critical path is the longest route through the network. A delay to an activity on this path extends the path and delays project completion.
- Use and update the plan. Use the critical path for monitoring as well as planning, and update the network to reflect progress.
Float, Multiple Paths, and Resources
CPM calculates the earliest and latest possible start times for activities. The difference indicates where an activity has float, often called slack: the amount its start time can vary without affecting the project’s completion date.
A project can have more than one critical path. The speaker suggests that if every route through the network has the same duration, the project could be considered optimized. However, this also leaves maximum risk because all resources are fully deployed. Parallel paths require enough resource flexibility to assign resources in line with the plan.
CPM and Gantt Charts
The speaker describes CPM as a strong way to understand project logic and calculate duration, while noting that many project managers prefer Gantt charts. A Gantt chart and a CPM network diagram are different representations of the same underlying information. Project-planning tools can display that information in either format.
Speakers and Sources Mentioned
- Speaker: Dr. Mike Clayton, the presenter.
- People and organizations: Morgan Walker and DuPont; James Kelly and Remington Rand; Booz Allen Hamilton and the US Navy, associated in the video with PERT.
- Historical project: The Manhattan Project.
Rate this summary
Your feedback will help improve summaries.
Improve this summary
Reprocess with a stronger model when the summary feels incomplete or inaccurate.
Translate summary in another language
Ask questions to this video
Chat for follow-up questions, clarifications, and source-backed answers.