Project Management: Finding the Critical Path(s) and Project Duration
Main summary
Key takeaways
Summary
The video demonstrates how to draw a project network diagram, identify all start-to-finish paths, and determine the critical path and overall project duration.
Activities and dependencies
- A has no predecessor.
- B and C both follow A.
- D follows B.
- E requires both B and C to be completed.
- F requires both D and E to be completed.
Activity durations
Activity Duration A 3 B 5 C 4 D 6 E 7 F 4Finding the critical path
- Draw a network diagram showing the activities and their dependencies.
- List every path from the first activity to the final activity:
- A → B → D → F: 3 + 5 + 6 + 4 = 18
- A → B → E → F: 3 + 5 + 7 + 4 = 19
- A → C → E → F: 3 + 4 + 7 + 4 = 18
- Compare the path durations. The longest path is the critical path.
- The critical path is A → B → E → F, which takes 19 days. Therefore, the project duration is 19 days.
The project’s duration is determined by its longest dependency path. Activities on that path must be completed in sequence before the project can finish.
Speakers or sources featured
- One unnamed speaker or instructor presents the example. No other speakers or sources are featured.
Rate this summary
Your feedback will help improve summaries.
Improve this summary
Reprocess with a stronger model when the summary feels incomplete or inaccurate.
Translate summary in another language
Ask questions to this video
Chat for follow-up questions, clarifications, and source-backed answers.